Schedule of Activities
Our projects in the Perth Basin cover the various stages of project life-cycle. Following are anticipated timings for key activities. Please note, timings provided are indicative only and subject to change.
Waitsia Stage 1: Production
Production continues. Xyris Production Facility capacity is 30 Terajoules (TJ)/day.
Ongoing.
Waitsia Stage 2: Construction of Waitsia Gas Plant
Waitsia Gas Plant Facility will have 250TJ/day capacity.
Scheduled for completion Q2 2025.
Flowline and hub construction activities
Connecting PL128 pipeline with PL124 pipeline.
Completed March 2025.
L1/L2: Arenaria-1
Exploration well
Completed April 2025.
EP455, L4, L5: Stockyard
2D Seismic Survey
Commenced March 2025.
EP413: Arrowsmith
Airborne Surveys - AGG and Apis AMAG (Part 1)
Completed December 2023.
L4/L5 well: Woodada-12
Plug & Abandonment activities
Woodada-12 well head cut scheduled for June 2025.
L4/L5 well: Woodada-15
Plug & Abandonment activities
Woodada-15 well head cut scheduled for June 2025.
L1/L2: Senecio-02, Centella-01, Snottygobble-01, Hovea-08, Eremia-01
Plug & Abandonment activities
Well head cuts scheduled for July 2025.
Dongara Production Facility
In 'Care and Maintenance'. Operations have ceased.
Processing equipment was decommissioned, removed and recycled early in 2021.
Hovea Production Facility
In 'Care and Maintenance'. Operations have ceased.
Processing equipment was decommissioned, removed and recycled early in 2021.
Woodada Production Facility
In 'Care and Maintenance'. Operations have ceased.
Processing equipment was decommissioned, removed and recycled early in 2021.