Schedule of Activities
Our projects in the Perth Basin cover the various stages of project life-cycle. Following are anticipated timings for key activities. Please note, timings provided are indicative only and subject to change.
Waitsia Stage 1: Production
Ongoing.
Waitsia Stage 2: Construction of Waitsia Gas Plant
Scheduled for completion Q2 2025.
Waitsia Gas Field: Site Preparation & well pad construction
Scheduled October 2024 - January 2025.
Flowline and hub construction activities
Timing to be advised.
L1/L2: Arenaria-1
Anticipated to commence March 2025.
EP455, L4, L5: Stockyard
Scheduled March/April pending approvals.
EP413: Arrowsmith
Completed December 2023.
L4/L5 well: Woodada-12
Woodada-12 to commence P&A from 15 January.
L4/L5 well: Woodada-15
Woodada-15 anticipated to commence end of January 2025.
Dongara Production Facility
Processing equipment was decommissioned, removed and recycled early in 2021.
Hovea Production Facility
Processing equipment was decommissioned, removed and recycled early in 2021.
Woodada Production Facility
Processing equipment was decommissioned, removed and recycled early in 2021.