You’re reading: Schedule of Activities
You’re reading: Schedule of Activities

Schedule of Activities

If you have any questions, feedback, compliments or complaints about Mitsui E&P Australia’s projects or operations in the Mid West, please contact us by filling in the form below and we’ll get back to you as soon as possible.

Waitsia Gas Project

Eremia-04

Work Over.

Scheduled January 2027.

Waitsia-01

Work Over.

Scheduled December 2026.

Planned Gas Plant Turnaround

Planned Turnaround Activity at the Waitsia Gas Plant.

Scheduled September 2026.

First Gas Out

Commencement of first gas out from Waitsia Gas Plant.

Achieved December 2025.

Ready For Start Up (RFSU)

Successful commissioning of all critical systems and components within the Waitsia Gas Plant.

Achieved November 2025.

Waitsia Stage 2: Construction of Waitsia Gas Plant

Waitsia Gas Plant Facility will have 250TJ/day capacity.

Completed July 2025.

Flowline and hub construction activities

Connecting PL128 pipeline with PL24 pipeline.

Completed March 2025.

Waitsia Stage 1: Production

Production continues. Xyris Production Facility capacity is 30 Terajoules (TJ)/day.

Ongoing.

EP413: Sarabes Onshore 2D Seismic Survey

2D Seismic Survey.

Scheduled Q4 2026 / Q1 2027.

Waitsia South-1 and Stawellia-1 Exploration Wells

Drilling.

Scheduled Q1 2027.

Waitsia South-1 and Stawellia-1 Exploration Wells

Earthworks.

Scheduled Q4 2026.

L1/L2: Arenaria-1

Exploration well.

Completed April 2025.

EP455, L4, L5: Stockyard

2D Seismic Survey.

Completed April 2025.

EP413: Arrowsmith

Airborne Surveys – AGG and Apis AMAG (Part 1).

Completed December 2023.

EP413: Arrowsmith-02

Plug & Abandonment activities.

Scheduled Q4 2026.

L4/L5: Woodada-16, Woodada-10, Woodada Deep-1, East Lake Logue-02

Plug & Abandonment activities.

Scheduled Q3 and Q4 2026.

L4/L5: Woodada-06, Woodada-08, Woodada-19

Plug & Abandonment activities.

Completed 2026.

L1/L2: Corybas-1, Xyris South-1

Plug & Abandonment activities.

Completed 2026.

L4/L5 well: Woodada-12

Plug & Abandonment activities.

Completed June 2025.

L4/L5 well: Woodada-15

Plug & Abandonment activities.

Completed June 2025.

L1/L2: Senecio-02, Centella-01, Snottygobble-01, Hovea-08, Eremia-01

Plug & Abandonment activities.

Plug & Abandonment activities Completed July 2025.

Phase 3 Woodada Gas Field

Decommissioning and rehabilitation (final).

Anticipated to commence 2027.

Woodada Gas Field

Phase 2B Decommissioning and rehabilitation.

Completed May 2025.

Seed collection

Rehabilitation activity.

November 2024 – April 2025.

Post rehabilitation monitoring

Annual Activity.

Annually from Spring 2024.

Baseline environmental monitoring

Targeted flora and Black Cockatoo habitat and foraging survey.

Spring 2023.

Woodada Gas Field

Phase 2A Decommissioning and rehabilitation.

Completed April 2023.

Woodada Production Facility

In ‘Care and Maintenance’. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.

Woodada Production Facility

In ‘Care and Maintenance’. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.

Woodada Gas Field

Phase 2A Decommissioning and rehabilitation

Completed April 2023.

Woodada Gas Field

Phase 2B Decommissioning and rehabilitation.

Completed May 2025.

Baseline environmental monitoring

Targeted flora and Black Cockatoo habitat and foraging survey.

Spring 2023.

Post rehabilitation monitoring

Annual Activity

Annually from Spring 2024.

Dongara Production Facility

In ‘Care and Maintenance’. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.

Hovea Production Facility

In ‘Care and Maintenance’. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.

Woodada Production Facility

In ‘Care and Maintenance’. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.